All tags with text shall be in English.
Earthing System
All normal non-current carrying metal parts of the panel and related parts shall be secured to a common aluminum
earthbar running the whole length in the switchboard.
The earthbar shall be found in the lower part of the frame work and supplied with two termination points for
connection to the main earthing grid.
2.5 Ignition Oil Supply
MEDICAL WASTE INCINERATOR INTALI8ATION
Design, Supply, install, test and commission medical waste
Incinerator According to the attached specification. The price shall
include all accessories such as the civil work and spare part
list to make the system complete.
incinerator burning capacity-250kg/hr NO 1
Jimma University Referal Hospital
Incinerator
Medical Waste Incinerator
Purpose
for an entire destruction of waste from various hospital services by heat treatment of high temperature in accordance
with EU standard on emission requirement
Waste from health care activities
Infections waste, lab cultures, waste form operation room isolations material in contact with contaminated
patients, waste potentially being infected by pathogenic agents.
Pathological waste, human fragments, bold, fetus, all body fluids, human cells.
Sculpts, needles, infusion sets, blades, glass
Pharmaceutical waste.
Chemical waste lab reagents, disinfectants
Expired drugs.
Medical waste incinerator: – Ecological Requirement
-No odor
-No fume
-Definitive treatment of waste
Medical waste incinerator: – Manufacturing Standards
-UL, CE, ASME, ISA EURO emission standard
1. Medical waste incinerator
Construction- CS plate shells, FB reinforcement, caste refractory linings,
insulation and 14 gage aluminum coat.
Type of fuel- Oil fired (Diesel)
Burning Capacity- 250kg/hr and moisture up to 80%
Duration-8-16/Continuous
Average fuel consumption- Really little as much as possible
Control Form – PLC based operation
Operating Temperature- Primary chamber 800c± 50
– Secondary Chamber 1050c ± 50
Size of incinerator — Not over 15mx7.20m
Chimney — Q630x25meter height and 7mm thick CS.
Combustion efficiency — 99%
Mode of waste handling — Semi- Automatic via ram loader.
Mode of ash handling — Semi- automatic via grate and ash trolley.
Pollution control equipment- Dry settlement zone
Doors — 1- waste charging door in main chamber
1-Clinker door in main chamber
1-Ash trolley access door in main chamber
1-Clean entrance door in secondary room
Burner -2- ignition burner in main chamber
2-after burner in secondary room.
Sort – package mono block-fully automated
Type of burner operation- modulation controller
Forced draught fan- 1- primary air fan
1-secondary air fan
Fuel storage tank- Capacity-2500liter over grond
– Material -6mm thick mild steel
-2-gas pump, gate valve, sfety valve, strainer
pipe, pressure gage, check valve, control board
Level indicator. Etc
Refractory/insulation thickness- not less than 225mm
Ram loader capacity-0.75m3
Electrical provide -380v/3ph/50 Hz
Finish and painting type- powder coated
Audio/Visual alarm system- burner lockout, overload fault
Electrical accessories — primary and secondary chamber temperature
Controller /indicator, auto controls, electric
Control switches, push buttons, relays contavtors
Thermocouples, burner sequence controllers,
Timers, emergency stop and alarms.
Level indicator. Etc
Refractory/insulation thickness- not less than 225mm
Ram loader capacity-0.75m3
Electrical supply -380v/3ph/50 Hz
Finish and painting type- powder coated
Audio/Visual alarm system- burner lockout, overload fault
Electrical accessories – primary and secondary chamber temperature
Controller /indicator, auto controls, electrical
Control switches, push buttons, relays contavtors
Thermocouples, burner sequence controllers,
Timers, emergency stop and alarms.